updated 03/30 |
Dream House Web Log |
Days 311-320 | |
|
|
The Dream is almost a reality. |
|
|
Watch our progress while we build |
||||
Construction Day 320 March 31, 2005 We teamed up to get the glass block installed in the wall of the laundry room. It will end up as a side light to the entrance to the room. We used the same glass block that is in the master shower (since we happened to have just enough blocks left over).
|
|
|||
Construction Day 319 March 30, 2005 Brian is finishing the puttying, sanding, and painting of the hot tub room window. He is also prepping the wall in the laundry room to accept installation of glass blocks. In the meantime, Daniel is unwrapping the hot tub to inspect it before it moves into its permanent location. We have not seen the tub in almost two years. |
|
|||
|
||||
Construction Day 318 March 23, 2005 All the tile work is finally complete except for needing to be dusted. We added a little extra detail into the skylight above the hot tub. |
|
|||
Brian has completed the framing for the wall in the staircase. We are scheduling the drywall crew to return and finish the new wall. |
|
|||
Construction Day 317 March 22, 2005 The floor tile is down and ready to be grouted. Tomorrow all the tile work should be complete. Brian is almost completed with the framing of the stair dividing wall.
|
|
|||
Construction Day 316 March 21, 2005 The tile guy showed up for 5 minutes, but decided he still needed more materials to start the floor. In the meantime, Brian is deconstructing and reconstructing the center wall in the staircase. We are raising it 39" so that we can avoid having to use balusters on the stair railing. After Brian completes the raising, we will have to have the drywall crew return to mud and tape the new wall. |
|
|||
|
||||
Construction Day 315 March 15, 2005 The grouting of the walls is complete and it looks great. We used canvas colored grout to match the tiles. Tomorrow they will start tiling the floor. |
|
|||
Construction Day 314 March 14, 2005 The stripe is finally being placed into the hot tub room wall. This step completes the tile for the walls and now it can be grouted. |
|
|||
Construction Day 313 March 11, 2005 The tub surround is being grouted and the hot tub room walls are almost finished. |
|
|||
It is tough to get a good angle for a picture of the tub surround but here is a three frame view to see all the sides. |
||||
|
||||
Construction Day 312 March 10, 2005 |
|
|||
Construction Day 311 March 9, 2005 Work continues on the tub surround, and the tile has almost reached the ceiling.
|
|
|||