updated

05/17

Dream House Web Log

Days

91-100

 

 

                    See it live if Brian's web cam is running.  WebCam

Watch our progress while we build

   

Construction

Day 100

May 13

 

 

The shingles for the roof were delivered and should be installed tomorrow.

 

The garage roof passed inspection and the house should pass tomorrow.

 

We passed the Mechanical inspection.  The Inspector was impressed with the job the A/C installers did.

The framers are still working to finish the soffit over the front porch.

 

Construction

Day 99

May 12

 

The electricians are back and continuing to run wires.  The framers are putting up the soffit over the front porch.

The dry-in inspection for the garage roof is scheduled for tomorrow.  The roofers will complete a small area of flashing on the house and the house will be ready for inspection, too.

 

Construction

Day 98

May 10

 

The facia across the front is complete and looks really good.  The soffit above the porch is going on next.

The electricians are still running wires and installing recessed lights.  There is a lot of wire and lights.

 

Construction

Day 97

May 9

 

FINALLY!!!!  The roofers are here and the roof is being "dried in" and all the flashing is being installed.  The metal drip edge is also being completed.

Fuck you, Paul.

 

Brian is helping install the skylight over the hot tub.

Construction

Day 96

May 7

The electricians are still running wires and installing recessed lighting.

Construction

Day 95

May 5

The framers are finishing up.  We are having them replace a lot of the facia and soffit installed because it looked like shit they way they installed it.

Construction

Day 94

May 2

The electricians are running wires and installed the recessed lighting.  The A/C installers are almost finished.

The photo shows looking up to the oculous and second floor ceiling from the rotunda.  Visible is the ducting for air conditioning and the copper cables run for the lightning rods.

Construction

Day 93

May 1

The electricians continue with running wire and placing outlets.

Construction

Day 92

April 30

The electrician is here starting the interior work.  The lightning rod interior installation is almost complete.

Construction

Day 91

April 28

The ducts for the A/C installation are complete.
   
 

 

 

 

 

return to main page