updated

12/17

Dream House Web Log

Days 191-200

 

 

 

                      Watch our progress while we build

   

The Orlando Sentinel has been running a great series of articles on home building in Central Florida.  Here is a link to the articles and an interesting (and totally unrealistic to our project) sidebar on the timeline for construction.

BUILDING HOMES: BUILDING PROBLEMS

  • Search our database.
  • How we did it.
  • See our photo gallery of Mexican migrants
  • Watch video, see photos and graphics
  • PHOTO GALLERY

    What you need to know when having a home built
    What you need to know when having a home built (LOUIS SPIRITO/ORLANDO SENTINEL)

     

       

    Construction

    Day 200

    December 16

    The painters continue on the exterior applying the 2nd and 3rd coats of color.

    TRIVIA:  We broke ground 19 months ago.  The Empire State Building was built in 16 months.

       

    We have finalized the order of some custom tiles for the tub surround.  Here is a picture of two prototype tiles to give an idea how the tiles will look.

       

    Construction

    Day 199

    December 15

    The Pro's are coming... the Pro's are coming!  Finally, we have professionals here to paint the exterior of the house and garage.

       
     

       
     
       

    Construction

    Day 198

    December 13

    After a great vacation, we are back to priming.
       

    Construction

    Day 197

    December 02

    Brian is applying the last of the exterior sealer to the stucco since the exterior painters are scheduled to start on the 11th.

    Inside we are still "cutting in" the drywall primer.

       

    Construction

    Days

    195 & 196

    November 29 & 30

    We are doing the "cutting in" and have completed the kitchen and the bar area.  We are looking at days and days for painting.
       

    Construction

    Day 194

    November 28

    Today, we started putting the primer paint coat onto the interior walls.  Daniel does everything from 5' and up and Brian does everything from 5' and down.

       

    Construction

    Day 193

    November 26

    Brian is working on the second floor deck.  Daniel is making architectural drawing for quotes on shelving, tile and solid surfacing.

     

    These are Daniel's drawing:

    Fair Warning: these links probably won't work on your computer

     

    Proposed Placement Survey

     

    Elevation Survey

     

    2nd Floor Deck Placement

     

    Dressing closets and Master shower layout

       

    Construction

    Day 192

    November 21

    No hired help today, but we are priming the deck frame and vacuuming up the drywall dust inside.

       

    Construction

    Day 191

    November 12

    Today's crew is applying the stucco to the lathe.

       
     

     

     

     

     