Days 291-300 | |
|
|
The Dream is almost a reality. |
|
|
Watch our progress while we build |
|
Construction Day 300 February 10, 2005 Tile in the hot tub room is still being installed. Brian is working on a few projects including building a wood duck nesting box. Daniel is drawing out the bar plan and ordering the underbar equipment thanks to a special little connection in the foodservice industry. |
|
Construction Day 299 February 9, 2005 |
|
Construction Day 298 February 7, 2005 The tile guy is back and continuing to work on the wall tile in the hot tub room. Also, we caught the County Property Appraiser sneaking around peeking in windows. Apparently the County is anxious to start collecting some taxes on this house, but they can't until we get the Certificate of Occupancy.
|
|
Construction Day 297 February 4, 2005 It's been a while since we've had two trades in at once. The tile guy made it back to begin on the hot tub room, and the glass crew is here installing the glass enclosure for the master shower and the sliding doors for the hot tub room. |
|
Two steps forward, and one back. The sliding doors are the reverse of what they are supposed to be so new panels will have to be ordered. |
|
At least the tile seems to be going right. The tile guy only worked for a couple of hours today, but it's a start. |
|
Construction Day 296 February 3, 2005 Another late start and no helper (other than Brian) but tile is going up. But... apparently, it is just a half day for the tile guy. At least, the tile is all in place for the shower stall. We also got approval from the building inspector for the guardrail planned for the 2nd floor. Now, we just have to find a company that can manufacture it. The installation of the glass enclosure for the Master shower is scheduled for tomorrow morning. |
|
Construction Day 295 February 2, 2005 OK... so tile only gets installed every other day... must be a union thing. The tile guy is back, again, and the mounting of the tile for the downstairs shower is almost complete. The tile still has to be grouted, but that is apparently a different person's job. The layout of the shower makes it very difficult to get a good picture to show the tile work, but here is a drawing of the design to show the pattern. The red lines mark the corners where the pattern wraps the wall. |
|
Construction Day 294 January 31, 2005 Better late than never... the tile guy is back and should be finishing the downstairs shower. We have moved on to prepping the tub surround for the tile installation there. The glass enclosure for the Master shower and the sliding glass panels for the hot tub room were supposed to be delivered today. |
|
Construction Day 293 January 30, 2005 |
|
Construction Day 292 January 28, 2005 After a "no call/no show" yesterday, the tile guy has returned with a "helper."
|
|
We are finishing the reapplication of the hot tub room ceiling so it is ready for the tile. Brian is trimming the concrete backer boards to get the best fit. |
|
Construction Day 291 January 26, 2005 The installation of the tile for the downstairs shower continues. |
|
We are also continuing to work on the ceiling base in the hot tub room. |
|