Days 251-260

 

 

 

     

 

The Dream is almost a reality.

 

 

                      Watch our progress while we build

   
   

Construction

Day 260

July 20, 2004

Jeff is back and is installing the vinyl flooring in the upstairs bathrooms.

 

   

The floor for the Master Bath is complete.  The small closet next to the bath also received a vinyl floor. 

The custom Corian shower pan should be installed next week.

   

Working late into the the night Jeff finishes the final bathroom, the laundry room, and the linen closet.

   

The floor is finished in the 2nd upstairs bath and now we can move forward with the cabinets.  We are still waiting on the custom tile for the tub surround.

   

Construction

Day 259

July 10, 2004

The electricians are here working on trimming out the outlets and switches inside the house.

Brian completed another section of his landscape wall so we can grade around it.

   

Construction

Day 258

July 6, 2004

We are still working outside on grading.  We have extended a landscaping  wall next to the garage and moving a truckload of sand.

   

Construction

Day 257

June 29, 2004

We are back to working on the grading and drainage of the far side of the house.

We have selected a new company to fabricate the Corian shower for the Master Bathroom.  They will be out Thursday to make the template.

   

Construction

Day 256

June 26, 2004

We are working on several small projects around the house.

Brian is sanding and shaping the countertop for the downstairs bathroom so it will have a great custom fit from a pre-fab, solid-surface countertop and integrated sink.

We are still working on prepping the floors for covering.  The floor in the upstairs bathrooms are ready for installation.  We have also finished scrubbing the rest of the floors to remove the excess plaster and mud from the drywall and texture installation.

   

We have picked up the floor covering for the two bathrooms upstairs.

Product Image         Product Image

Twinkle Moonbeam White                       Chestnut Lane Dusty Blue

We also picked up the bamboo wood flooring for the entryway and the bar.

           Bamboo Vertical Spice
   

De-Construction

 

June, 2004

We have lost another tree due to construction nearby.  Unfortunately, this one is 50'+ high with thick, heavy limbs that could really do some damage.

Brian starts off by climbing 40' up and taking off most of the large branches.

 

   

Then just as the sun is setting, Jeff comes over to help us cut down the remains of the tree.  Jeff cuts while Daniel & Brian pull on a rope attached around the top of the tee.

It was a little nerve wrecking since the tree was only 20' from the new garage.  After a lot of strained muscles and almost an hour, the tree was safely down right where we planned it.

   

The garbage men are pissed at us for how much yard trash we have been putting at the curb.  We are left with the thickest part of the tree and the truck to dispose of.

   

Construction

Day 255

June 19, 2004

We are installing some outside drainage pipes to help reduce the erosion until we get sod in place.  The grates will stay in place after sod is installed to catch runoff in areas where we are not installing gutters.

   

Construction

Day 254

June 9, 2004

We installed the vanity cabinet for the downstairs bath.

Brian is still working on the second floor deck.  Daniel is prepping the front bathroom for floor covering.

 

   

Construction

Day 253

June 2, 2004

The painting is complete for the downstairs bathroom.  We call the color, "Wow! That's white!"

Thanks to a neighborly kind of guy, the flooring for this bathroom is installed, too.

Tile for the shower stall is schedule to be installed next week.

The plan for this bathroom is just black & white.

Product Image    Corner Dot Black

   
  NOTE 06/01/04:  We picked up some of the interior doors for the 1st floor, and we ordered the double 8' doors for the entryway closets.  Also, we are picking up more tile and getting more tile installation quotes.  We are also trying to find a new builder's risk insurance policy.
   

Construction

Day 252

May 31, 2004

We finished the first coat of paint on the first floor bathroom.

Brian is working on various projects that complete a lot of little details so we can keep moving forward.

We also picked up the wood flooring for the bar and entryway.

We found a little time to enjoy some fun on the lake and took a picture to show the view from the water.

   

Construction

Day 251

May 26, 2004

Brian continues to work on the second floor deck.  It is a project that fills in when we are not working on anything else.

   
 

 

 

 

 

 