The Dream is almost a reality.

 

 
   
 

Watch our progress while we build

   

Construction

Day 290

January 25, 2005

The Tile Man stayeth!

Tile installation has commenced.  One guy with a slow pace, but so far, it is looking good.

   

The pattern is beginning to show.

   

Construction

Day 289

January 24, 2005

The Tile Man cometh, and the Tile Man goeth away.  The Tile Man returneth, and the Tile Man leaveth again.

In the meantime, we are dismantling the ceiling in the hot tub room in order to put a layer of plywood up.  This will better strengthen the ceiling for the weight of the tile.

No sign of the Tile Man coming back so we will have to wait until tomorrow to see if anyone shows up.

   

Construction

Day 288

January 17, 2005

The glass company was out to give a quote on the custom shower stall enclosure and the sliding glass panels for the hot tub room.

We are prepping the hot tub room for tile installation.  We are adding a little additional insulation to the interior wall, and we are carving out the drain in the floor.  Also, we are priming, puttying, filling, sanding, and painting the hot tub room window so it is ready for the tile installation.  The tile installer was supposed to be here today.

Brian is practicing and learning how to install the baseboard trim.

   

Construction

Day 287

January 11, 2005

Brian is working on several projects.

   

Construction

Day 286

January 10, 2005

The electrician has returned to get more work completed.  He is working on the security lights, electrical outlets, range outlet, deck lights and low-voltage lighting.

Brian is working on detailing the downstairs shower stall in preparation for the tile installer who called to say he is behind schedule.  Brian also is resealing the security lights, and finishing some of the interior light fixtures.

   

Daniel is working on getting quotes for stairs, handrails, and his pet project the guardrail for around the opening in the floor on the 2nd level of the rotunda.  The idea is to have something custom made that looks like the picture at the right (which happens to be the railing in Mr. Graves' personal residence).

We are both making trips to try and find carpeting for the downstairs great room.  That is the only selection left to be made.

 

Construction

Day 285

December 27, 2004

Progress, thy name is Paul.

Our friend Paul made his annual pilgrimage to provide a day of labor toward our little construction project.  Thank goodness.  Because of Paul's help, the framing for the second floor deck is complete.

 

   

Paul enjoyed playing with a different tool as he earned a skill badge in Palm Nailer Skill.

 

Brian and Paul also worked on re-installing the tile backer boards in the downstairs shower stall.

   

Construction

Day 284

December 7, 2004

The custom shower pan for the downstairs is complete and installed.

The A/C contractor is completing installation of the thermostats, grills, and the exhaust fan that was left off the laundry room.

We have laid out the pattern for the tub surround.  We have mixed the custom created tiles with off-the-shelf tiles to match the color variations in the custom tiles.

   

Construction

Day 283

December 3, 2004

 

Brian is working on installing the interior doors for the under-the-stairs storage and the downstairs bathroom.

Brian is also working on several miscellaneous projects including a bit of the second floor deck, grading in the backyard, and re-installing the shower walls downstairs.

In the downtime, we are finalizing the quote for tile installation, designing and ordering the glass shower enclosure for the master bath, and trying to stay motivated.

   

Construction

Day 282

November 22, 2004

The custom Corian shower pan for the downstairs shower has been installed.  It still requires some trim pieces that will be added soon.

   
 

   

Construction

Day 281

October 31, 2004

We have painted the hallway wall and it is ready for the A/C crew to install the thermostat and the electricians to install the doorbell chime.

We have also picked up an end panel for the Master Bath cabinet to install, and we have ordered the carpet for the upstairs.

The custom shower pan for the downstairs bath is schedule for installation on Monday.

   
 

 

 

 

 