updated 12/28 |
Dream House Web Log |
Days 271-280 | |
|
|
The Dream is almost a reality. |
|
|
|
Watch our progress while we build |
Construction Day 280 October 29, 2004 |
|
Construction Day 279 October 14, 2004 The power company has finally come back and have trenched from the street to the house. They are running the electric power lines deep underground because they feared someone like Brian would hit them with a shovel. We also have picked up the last of the custom tile for the tub surround. |
|
Construction Day 278 October 11, 2004 |
|
Construction Day 277 October 8, 2004 |
|
Construction Day 276 October 7, 2004 We are buzzing with activity as the full complement of electricians have returned and are working on finishing all the electrical connections in the house. The electrical connections to the detached garage are being installed. The wire has to be trenched and buried which also requires an inspection. |
|
Construction Day 275 October 6, 2004 A smaller swarm of electricians have returned, today. Working inside on a lot of projects and working outside on the higher, exterior lights. |
|
The electrician is modifying the electrical boxes to meet the new requirements of Progress Energy. The nerve of them to change the requirements after we started building. |
|
Also, the Corian countertops in all the bathrooms are being installed. |
|
Construction Day 274 October 5, 2004 |
|
Construction Day 273 September 19, 2004 Working on a few smaller projects around the house. Now that our scaffolding is back from being out on loan, Brian is working on the second floor deck and installing the recessed lights and ceiling fan at the 18' height. Daniel is working on cleaning up after the last few crews and repairing the driveway after having the dumpster removed. |
|
Construction Day 272 September 7, 2004 |
Just a day after a hurricane and days before another is scheduled to visit, we were busy cleaning up storm debris when the A/C crew showed up to install the outside heat pumps. They did not even call to see if we were alive or if the building was still standing. So, we had a day of progress instead of clean up, but both heat pumps are installed and the interiors grills are in place. The crew was really surprised when I requested they wrap and protect the outside units to minimize damage from the on-coming hurricane. |
|
NOTE 09/04/04: Hurricane Frances is headed in, and we still have a small leak that we think is finally patched. We did have a unusual sunset thanks to Frances. |
Construction Day 271 September 3, 2004 Since we have company arriving tomorrow (Aunt Frances the Blowhard), we are installing the air handlers and filters for the HVAC system. |
|